Average Solar Permit Timeline By State: Complete Guide

Solar permit and interconnection approval times in the United States range from 25 to 64 days, depending on your state. The process involves four distinct phases: local authority (AHJ) permit review, pre-installation utility interconnection evaluation, physical system inspection, and post-installation grid connection authorization.

Quick Answer: Solar Permit Times by State (2024 Data)

Fastest States (25-30 days):

  • New York: 25 days (7 permit + 5 pre-interconnection + 10 inspection + 3 post-interconnection)
  • Nevada: 27 days (0 permit + 0 pre-interconnection + 8 inspection + 19 post-interconnection)
  • California: 28 days (6 permit + 0 pre-interconnection + 18 inspection + 4 post-interconnection)
  • Texas: 29 days (9 permit + 4 pre-interconnection + 9 inspection + 7 post-interconnection)
  • Illinois: 30 days (9 permit + 1 pre-interconnection + 11 inspection + 9 post-interconnection)

Mid-Tier States (34-47 days): Arizona (34), Florida (34), Massachusetts (39), Georgia (45), Virginia (47), Ohio (47)

Slowest States (51-64 days):

  • New Jersey: 51 days
  • Michigan: 53 days
  • Colorado: 54 days
  • North Carolina: 59 days
  • Pennsylvania: 64 days

What Makes States Faster?

States with automated platforms like SolarAPP+ reduce review times from 20 business days to zero, cutting total project timelines by up to 12 days. Additional acceleration factors include:

Data Source & Methodology

This analysis uses 2022 data from NREL's SolarTRACE platform, examining median approval timelines for residential solar installations under 10 kilowatts (kW) across 16 major U.S. solar markets: Arizona, California, Colorado, Florida, Georgia, Illinois, Massachusetts, Michigan, Nevada, New Jersey, New York, North Carolina, Ohio, Pennsylvania, Texas, and Virginia.

two people discussing approval permit

Evaluation Methodology for Solar Approval Workflows

Our analysis incorporated multiple data sources to assess permitting efficiency across various states. Drawing from 2022 information available through NREL's SolarTRACE platform, we evaluated typical durations for permit submission, pre-installation grid reviews, physical inspections, and post-installation connection authorizations. These benchmarks provide valuable insight into regional processing speeds.

The research additionally examines state-level initiatives designed to expedite and enhance approval procedures. Such initiatives encompass standardized submission protocols, digital application portals, and strategies aimed at minimizing bureaucratic obstacles for installation professionals.

SolSmart Recognition Program

Numerous municipalities and counties nationwide have received SolSmart distinctions. This nationally recognized designation honors communities that have simplified and reduced costs associated with solar panel installation. Communities earn Gold, Silver, or Bronze status based on their implementation of solar-supportive policies across five evaluation areas: permitting and inspection procedures, planning and zoning regulations, governmental operations, public outreach initiatives, and market development strategies that foster local renewable energy adoption.

SolarAPP+ Platform

Certain jurisdictions have implemented SolarAPP+, a digital permitting solution engineered to simplify and expedite residential solar installation approvals. Our data references information from the National Renewable Energy Laboratory's database current as of September 30, 2023.

Geographic Coverage

This permit duration analysis encompasses Arizona, California, Colorado, Florida, Georgia, Illinois, Massachusetts, Michigan, Nevada, New Jersey, New York, North Carolina, Ohio, Pennsylvania, Texas, and Virginia, states representing some of America's most substantial solar energy markets.

How Long Do Solar Permits and Interconnections Take in Each State?

Median Solar Permitting, Interconnection, and Inspection Times in Days

State AHJ Permit Time Pre-Install Interconnection Time Inspection Time Post-Install Interconnection Time Average Total
New York 7 5 10 3 25
Nevada 0 0 8 19 27
California 6 0 18 4 28
Texas 9 4 9 7 29
Illinois 9 1 11 9 30
Arizona 9 7 7 11 34
Florida 9 0 14 11 34
Massachusetts 7 6 13 13 39
Georgia 8 11 8 18 45
Virginia 12 11 14 10 47
Ohio 17 10 11 9 47
New Jersey 15 7 21 8 51
Michigan 15 18 7 13 53
Colorado 8 10 16 20 54
North Carolina 9 8 24 18 59
Pennsylvania 16 23 12 13 64
```


Leading States for Rapid Solar Permit Approvals

States achieving the fastest processing times have deployed standardized submission protocols, uniform application documentation, and accelerated review schedules that enable swift permit authorization. These jurisdictions emphasize operational efficiency and procedural simplicity while maintaining regulatory compliance, minimizing bureaucratic obstacles, and catalyzing renewable energy expansion. Total approval duration—encompassing permit processing, inspection scheduling, and interconnection authorization; spans 25 to 30 days across these top-performing states.

New York: Nation's Fastest Solar Approval System

New York secures the top position for expedited residential solar permitting with a 25-day average completion timeline. The New York State Unified Solar Permit (NYS-USP) framework streamlines small-scale solar installation procedures through standardized application protocols. This program, operating under the NY-Sun initiative, targets reduction of expenses, procedural complexity, and waiting periods linked to residential and commercial solar panel deployment.

Multiple municipalities demonstrate leadership in approval simplification, particularly New York City. New Rochelle, New York City, and Syracuse provide digital submission portals, while Rochester delivers same-day in-person authorization. Notably, as of September 2023, no jurisdictions had implemented the SolarAPP+ system.

New York SolSmart Recognition:

  • Gold: Erie County, Orange County, New York City, Suffolk County
  • Bronze: Brookhaven, Huntington

Nevada: Instant Processing Excellence

Despite no authorities having jurisdiction (AHJs) implementing SolarAPP+ throughout Nevada, installation professionals experience exceptionally swift permitting, especially within Las Vegas. Accelerated inspection protocols advance project timelines. However, post-installation grid connection averages 19 days, representing the most prolonged phase in Nevada's approval cycle.

Las Vegas delivers digital submission capabilities, instantaneous online authorization, and immediate in-person processing without structural review mandates. Reno earned SolSmart Silver recognition and maintains online permitting infrastructure.

Nevada SolSmart Recognition:

  • Gold: Las Vegas
  • Silver: Reno
  • Bronze: Clark County

California: National Pioneer in Permit Streamlining

California establishes the national benchmark for streamlined solar authorization initiatives, transforming the approval landscape for PV installations. Legislative measures like the Solar Permitting Efficiency Act (AB 2188) have standardized workflows, eliminated administrative barriers, and expedited review cycles. These accomplishments advance widespread solar adoption while establishing a blueprint for other states pursuing accelerated renewable energy deployment.

California leads in SolarAPP+ implementation, with multiple jurisdictions, including Fresno, San Francisco, and Stockton, piloting or fully deploying the digital permitting platform. Major metropolitan areas maintain online submission systems. Additionally, Anaheim, Irvine, Long Beach, Los Angeles, Oakland, Sacramento, San Francisco, San Jose, and Santa Ana provide same-day in-person authorization. The state's 18-day average inspection duration can moderately extend installation timelines.

California SolSmart Recognition:

  • Gold: Berkeley, Concord, Cupertino, Davis, Fremont, Huntington Beach, Oakland, Palm Springs, Sacramento, San Francisco, San Jose, Santa Monica, Santa Rosa, Sonoma County, Torrance
  • Silver: Hawthorne, San Leandro
  • Bronze: Contra Costa County, Inyo County, Marin County, Redondo Beach, San Diego County, Santa Barbara County, Yolo County

Texas: Accelerated Permitting and Grid Connection

Texas municipalities and counties have established streamlined submission and inspection protocols that expedite solar system deployment. Swift inspection processes with an eight-day median duration advance project progression. This efficiency proves particularly evident in major cities like Austin and Houston, which allocate dedicated resources toward renewable energy initiatives. Primary Texas utilities, including Oncor and CenterPoint, have developed solar-supportive policies and specialized teams managing interconnection requests efficiently.

Houston pilots SolarAPP+ as Texas's sole AHJ utilizing the digital permitting system. All major metropolitan areas—Arlington, Austin, Dallas, El Paso, Fort Worth, Houston, and San Antonio—offer online submission capabilities, with Austin providing same-day in-person authorization.

Texas SolSmart Recognition:

  • Gold: Austin, El Paso
  • Silver: San Antonio, Brownsville
  • Bronze: Plano

Illinois: Fast-Track Permit Leader

Illinois installation professionals benefit from abbreviated permitting and interconnection timeframes comparable to Texas and California for photovoltaic (PV) systems under 10 kW. Additionally, Illinois enacted recent legislation accelerating commercial solar project authorization. Public Act 102-1123 standardizes municipal permitting for renewable energy facilities, encompassing solar and wind installations.

Digital submission infrastructure exists throughout most of Illinois's largest municipalities, though no AHJs have deployed the SolarAPP+ platform.

Illinois SolSmart Recognition:

  • Gold: Aurora, Carol Stream, Chicago, Deerfield, Elgin, Evanston, Freeport, Lake County, Mount Prospect, Rockford, Skokie, Urbana, Waukegan, Will County
  • Silver: Libertyville, Naperville, Schaumburg
  • Bronze: Cook County, DuPage County, Kane County, Lake Forest

States Demonstrating Moderate Processing Efficiency

These jurisdictions have advanced permitting streamlining efforts, frequently implementing standardized frameworks that yield reasonably efficient authorization timeframes for solar installations. Complete approval duration, including interconnection and inspection phases, ranges from 34 to 47 days across these mid-tier states.

Arizona: Streamlined Permit Operations

Arizona distinguishes itself through relatively efficient permit submission systems, characterized by optimized workflows and expedited evaluations. These programs simplify installation application procedures and reinforce the state's standing as a renewable energy adoption leader. Arizona particularly excels with rapid seven-day inspection timeframes.

Arizona's permitting achievements partially stem from SolarAPP+ adoption or pilot programs in select areas, including Tucson, Phoenix, Pima County, and Oro Valley.

Arizona SolSmart Recognition:

  • Gold: Pima County
  • Silver: Oro Valley
  • Bronze: Maricopa County, Sedona

Florida: Residential Approval Excellence

Select Florida AHJs have achieved significant advances in permitting process efficiency, enabling installation professionals to secure swift authorizations, particularly for projects under 10 kW. Multiple local jurisdictions have deployed measures simplifying and accelerating permit approval workflows, though no Florida jurisdictions utilize SolarAPP+.

Florida SolSmart Recognition:

  • Gold: Fort Lauderdale, Miami-Dade County, Orange County, Orlando, Palm Beach County, Pensacola, Pompano Beach, West Palm Beach
  • Silver: Alachua County, Boca Raton, Lakeland
  • Bronze: Tampa

Massachusetts: Progressive Permitting Simplification

The state deployed the Solar Massachusetts Renewable Target (SMART) Program, incorporating provisions that simplify permitting and interconnection procedures for solar initiatives. Massachusetts installation professionals typically encounter relatively smooth permitting workflows, though historical districts introduce distinctive obstacles, especially in heritage cities like Boston, Salem, and Cambridge.

No AHJs have initiated SolarAPP+ pilot programs or full implementation, but numerous cities, including Boston, Brockton, Cambridge, Fall River, Lynn, New Bedford, Quincy, and Worcester, maintain online submission capabilities. Boston and Lynn deliver same-day in-person authorization, while most larger municipalities mandate structural reviews for solar permit acquisition.

Massachusetts SolSmart Recognition:

  • Gold: Chelmsford, Lowell, Somerville
  • Silver: Framingham, Gloucester
  • Bronze: Boston, Cambridge

Georgia: Standard Processing Timeframes

Georgia's AHJs demonstrate relatively efficient PV permit processing, attributable partly to transparent permit guidelines. Through streamlined protocols, solar projects typically receive prompt evaluation, reflecting Georgia's renewable energy commitment and technology adoption facilitation across the state. Post-installation interconnection averaging 18 days moderately extends the overall timeline.

Atlanta, Columbus, and Savannah provide online permit submission platforms. However, no Georgia jurisdictions have implemented SolarAPP+.

Georgia SolSmart Recognition:

  • Gold: Atlanta
  • Silver: Doraville, Putnam County
  • Bronze: Athens-Clarke County, DeKalb County, Savannah

Virginia: Variable Processing Durations

Solar permit acquisition timeframes in Virginia fluctuate based on specific locality and PV project complexity. Nevertheless, numerous Virginia AHJs have implemented measures streamlining the permitting workflow, accelerating solar energy adoption.

Major Virginia cities, including Alexandria, Chesapeake, Richmond, Roanoke, and Virginia Beach, offer online submission systems, while Arlington provides same-day in-person authorization. Culpeper County and Harrisonburg are piloting SolarAPP+.

Virginia SolSmart Recognition:

  • Gold: Alexandria, Fairfax County, Norfolk, Richmond
  • Silver: Charlottesville, Harrisonburg, Loudoun County
  • Bronze: Albemarle County, Arlington County, James City County, Newport News, Roanoke, Tazewell County

Ohio: Extended Approval Cycles

Ohio's solar energy sector has experienced substantial utility-scale growth, elevating its position as an emerging market leader. Following a record-breaking year, Ohio reached fifth place for installed solar capacity. Despite this accomplishment, residential and commercial solar markets remain comparatively underdeveloped, with residential permitting averaging 47 days.

The Mid-Ohio Regional Planning Commission, OKI Regional Council of Governments, and select cities, including Columbus, have pursued permitting improvements. Unfortunately, several major Ohio cities lack online or same-day in-person submission capabilities, and no jurisdictions utilize the SolarAPP+ platform.

Ohio SolSmart Recognition:

  • Gold: Columbus, Cuyahoga County, Lancaster
  • Silver: Mid-Ohio Regional Planning Commission, OKI Regional Council of Governments
  • Bronze: Cleveland

States Experiencing Extended Solar Approval Timelines

Securing solar permits in these jurisdictions requires lengthier processing periods compared to previously discussed states. Nevertheless, select municipalities have initiated measures to optimize permitting workflows.

New Jersey: Prolonged Authorization Cycles

Despite the Solar Energy Industries Association ranking New Jersey ninth nationally for installed solar capacity with a substantial residential market, permitting cycle durations average 51 days, double New York's timeframe. Authority permitting, inspection phases both exhibit notably extended durations.

Among major cities and counties, only Camden County has earned SolSmart designation, while same-day in-person processing and online submission capabilities remain unavailable throughout much of the state. Additionally, no New Jersey jurisdictions have implemented the SolarAPP+ platform.

New Jersey SolSmart Recognition:

  • Bronze: Camden County

Michigan: Variable Processing Speeds

The permit submission workflow, encompassing AHJ authorization and PV interconnection phases, frequently progresses slowly in Michigan, though accelerated inspection protocols help expedite overall timelines. Local jurisdictions demonstrate varying approaches and requirements, with some deploying streamlined procedures to accelerate permit approvals while others maintain traditional processes.

Although Michigan solar system permitting can experience delays, certain cities—including East Lansing, Ann Arbor, Grand Rapids, and Detroit—now provide online submission platforms. However, no Michigan jurisdictions have adopted SolarAPP+.

Michigan SolSmart Recognition:

  • Gold: East Lansing
  • Silver: Ann Arbor, Grand Rapids, Lansing

Colorado: Time-Intensive Approval Workflows

Colorado derives over 9% of its electricity from solar energy and maintains robust utility-scale and residential solar markets. However, residential permitting can constitute a time-consuming endeavor, particularly for post-installation interconnection, though notable achievements exist. Colorado legislation caps residential PV permit costs at $500 and commercial installation permits at $1,000. Additionally, numerous Colorado municipalities pursue permitting enhancement initiatives.

Major cities including Arvada, Aurora, Boulder, Centennial, Colorado Springs, Denver, Fort Collins, Lakewood, Thornton, and Westminster offer online submission systems. Boulder, Colorado Springs, Denver, and Lakewood provide same-day in-person authorization, while Denver and Madera utilize the SolarAPP+ platform.

Colorado SolSmart Recognition:

  • Gold: Adams County, Boulder County, Clear Creek, Denver, Fort Collins, Garfield County, Jefferson County, Westminster
  • Silver: Boulder County
  • Bronze: Aurora, Lakewood, Pueblo County, Routt County, San Miguel County, Summit County

North Carolina: Extended Approval Durations

North Carolina ranks fourth nationally for installed solar capacity and maintains substantial utility-scale and residential solar markets. However, permit approval workflows can require extended durations, frequently spanning approximately two months. Inspection phases average 24 days for completion, combined with 18 days for post-installation interconnection.

Multiple cities have pursued solar permit simplification initiatives. Durham, Fayetteville, Greensboro, Raleigh, and Winston-Salem maintain online submission capabilities, with Raleigh offering same-day in-person processing. As of September 2023, no jurisdictions had deployed the SolarAPP+ platform.

North Carolina SolSmart Recognition:

  • Gold: Asheville, Cary, Chatham County, Durham City
  • Silver: Raleigh
  • Bronze: Greensboro

Pennsylvania: Inconsistent Municipal Processing

Pennsylvania solar permitting workflows vary substantially across municipalities. Some local jurisdictions have deployed streamlined procedures and standardized documentation to facilitate solar installations, while others maintain more complex systems with lengthier approval timelines. A 23-day average pre-installation interconnection process particularly hampers Pennsylvania solar permitting efficiency.

Philadelphia maintains online submission infrastructure, though no Pennsylvania AHJs have adopted the SolarAPP+ platform to optimize the permitting application workflow.

Pennsylvania SolSmart Recognition:

  • Gold: Chester County, Philadelphia
  • Silver: Montgomery County, Upper Darby Township
  • Bronze: Bucks County, Haverford Township, Lower Merion

Strategies for Expediting Solar Permit Authorization

Installation professionals can accelerate permit processing by satisfying all local and state authorization requirements while ensuring submitted information maintains completeness and accuracy. Submitting comprehensive permit applications featuring detailed plan sets and equipment specifications proves essential.

Additionally, confirming installations adhere to electrical and building code mandates while complying with local zoning regulations helps prevent processing delays. Implementing these practices enables installers to optimize permitting workflows and minimize obstacles or resubmission requirements. Working with professional solar design services can significantly streamline the approval process.

Key Acceleration Tactics:

  • Complete Documentation: Submit thorough plan sets with precise technical specifications
  • Code Compliance: Verify alignment with electrical, structural, and building regulations
  • Zoning Verification: Confirm project adherence to local land-use requirements
  • Accurate Information: Double-check all application data for errors or omissions
  • Standardized Formats: Utilize jurisdiction-preferred forms and submission templates

Following these protocols streamlines approval pathways, reduces back-and-forth communications with authorities, and accelerates project timelines from application submission through final authorization. Understanding what happens if you install solar panels without a permit underscores the importance of proper authorization.

Conclusion 

Solar permit and interconnection approval durations vary dramatically across the United States, ranging from New York's industry-leading 25-day timeline to Pennsylvania's extended 64-day processing cycle. Understanding these regional differences empowers installation professionals and property owners to set realistic project expectations, optimize deployment strategies, and identify opportunities for timeline acceleration.

The states achieving the fastest approval speeds, New York, Nevada, California, Texas, and Illinois, share common characteristics: standardized application protocols, robust digital submission infrastructure, automated review platforms, and streamlined inspection procedures. These jurisdictions demonstrate that regulatory efficiency and safety compliance can coexist when authorities prioritize process optimization and technological adoption.

Mid-tier states like Arizona, Florida, Massachusetts, Georgia, Virginia, and Ohio show promising progress through municipal-level initiatives, online permitting systems, and SolSmart program participation. While their 34-47 day timelines exceed top performers, ongoing improvement efforts signal commitment to accelerating renewable energy deployment.

States experiencing extended timelines, New Jersey, Michigan, Colorado, North Carolina, and Pennsylvania, face distinct challenges, including fragmented municipal requirements, limited digital infrastructure, and prolonged interconnection phases. However, select cities within these states have implemented successful streamlining measures, providing blueprints for statewide adoption.

The widespread implementation of automated platforms like SolarAPP+ has proven transformative, reducing traditional 20-business-day reviews to instantaneous approvals and cutting overall project timelines by up to 12 days. As more jurisdictions adopt these technologies alongside standardized procedures and transparent guidelines, the national solar deployment landscape will continue evolving toward greater efficiency.

For installers and property owners, success hinges on three critical factors: thorough documentation preparation, jurisdictional requirement research, and proactive engagement with local authorities. By submitting complete, accurate applications that satisfy all regulatory mandates, stakeholders can minimize delays and capitalize on available expedited processing options within their regions. Whether considering  professional installation versus DIY or exploring off-grid solar systems, understanding permit timelines remains crucial for project planning. For assistance navigating complex permitting requirements, contact our team or explore permit expediting services.

FAQs

What factors influence how long solar permitting takes in different states?

Solar permit duration depends on multiple interconnected factors, including local jurisdiction efficiency, digital infrastructure availability, standardized application protocols, inspection scheduling capacity, and utility interconnection procedures. States with automated review platforms like SolarAPP+, online submission portals, and unified application standards consistently achieve faster processing. Additionally, jurisdictions with dedicated renewable energy teams, transparent guidelines, and same-day processing options significantly reduce timelines. Municipal-level variations within states also create substantial differences; major metropolitan areas typically offer more streamlined processes than rural jurisdictions with limited administrative resources.

Which state has the fastest solar permit and interconnection approval process?

New York leads the nation with the fastest total approval timeline at 25 days on average, breaking down to 7 days for permit processing, 5 days for pre-installation interconnection, 10 days for inspection, and 3 days for post-installation connection authorization. This efficiency results from the New York State Unified Solar Permit (NYS-USP) framework that standardizes procedures for small-scale installations under the NY-Sun program. Nevada follows closely at 27 days with instant online permitting in Las Vegas, while California achieves 28 days through legislative streamlining initiatives like the Solar Permitting Efficiency Act (AB 2188).

How can solar installers speed up the permitting process?

Installers can accelerate approval timelines by submitting comprehensive applications featuring complete documentation, detailed plan sets, and precise equipment specifications from the initial submission. Ensuring installations adhere to electrical and building code requirements while complying with local zoning regulations prevents back-and-forth delays. Utilizing jurisdiction-preferred standardized forms, leveraging online submission portals where available, and maintaining proactive communication with authorities having jurisdiction (AHJs) streamlines workflows. Additionally, choosing jurisdictions with SolarAPP+ implementation, same-day in-person processing options, or online permitting infrastructure can dramatically reduce waiting periods. Double-checking all application data for accuracy before submission minimizes resubmission requirements. For those considering DIY solar installation, understanding these requirements becomes even more critical.

What is SolarAPP+, and how does it reduce permit processing times?

SolarAPP+ (Solar Automated Permit Processing Plus) is a free digital permitting platform that enables instant automated review of residential solar installation applications. Developed by the National Renewable Energy Laboratory (NREL) in partnership with the solar industry, this technology instantly evaluates permit submissions against local building codes and safety requirements, reducing traditional review times from up to 20 business days to zero. Jurisdictions that have implemented SolarAPP+ report projects being installed 12 days faster than those processed through manual review systems. The platform is expanding beyond solar to support additional home energy system types, with over 160 communities now offering instant approvals through automated processing.

Why do some states with large solar markets have slow permitting processes?

Market size doesn't always correlate with permitting efficiency due to infrastructure capacity constraints, fragmented regulatory frameworks, and varying municipal adoption of streamlining technologies. New Jersey, despite ranking ninth nationally for installed solar capacity, averages 51 days due to limited online submission availability and minimal SolarAPP+ adoption. North Carolina ranks fourth for total capacity but requires 59 days because of extended 24-day inspection periods and 18-day post-installation interconnection phases. Rapid market growth can outpace administrative infrastructure development, creating bottlenecks as permit volume exceeds reviewer capacity. Additionally, states with strong municipal autonomy may lack unified statewide standards, forcing installers to navigate varying requirements across neighboring jurisdictions. For comprehensive guidance on navigating these challenges, explore our complete solar permit guide or access SolSmart resources for best practices. Understanding solar radiation patterns can also help optimize system design for your specific region. Additional insights on global renewable energy trends, climate action initiatives, sustainable energy policy, and climate data provide valuable context for understanding the importance of streamlined solar permitting in achieving nationwide clean energy goals.

Contact us

Get in touch today

We are dedicated to providing top-notch solar permit services to homeowners, business owners, DIY, and solar installers. Contact us today.

Check - Elements Webflow Library - BRIX Templates

Thank you

Thanks for reaching out. We will get back to you soon.
Oops! Something went wrong while submitting the form.
Solar COMPANIES SUPPORTING
Solar Permit Solutions